MIRI: The relocation of the main water pipeline at Batu 7 along the Miri-Bintulu Road has entered the implementation phase following the completion of land acquisition and demolition works at the new site.
Works Minister Datuk Seri Alexander Nanta Linggi said the 4.2km utility relocation project under Package Work 11 (WPC11) of the Pan Borneo Highway is targeted for completion within three years, although it could be completed earlier given its importance to Miri residents.
He said the contractor would first build the new pipeline before decommissioning the existing one to ensure an uninterrupted water supply to consumers throughout the construction period.
“If we do not build the new pipeline first and proceed directly with the relocation, it would certainly disrupt the water supply to Miri consumers. Therefore, we will construct the new pipeline and, upon completion, carry out testing and commissioning.
“Only after confirming that water can be channelled through the new pipeline will we decommission the existing one,” he told a press conference after the groundbreaking ceremony for the Pan Borneo Highway (Miri Section) and the Miri Redline Short Stretch Project.
Nanta said the existing pipeline runs along the left side of the road towards Miri, while the new pipeline will be relocated to the right side.
He said land acquisition and the demolition of structures along the new alignment had been completed, allowing the contractor to begin construction of the new pipeline.
“If roadworks or road upgrading proceed without first relocating the pipeline, this could compromise the safety of the existing pipeline,” he said.
Last June, Sarawak Minister of Utility and Telecommunication Datuk Seri Julaihi Narawi said the long-term plan to relocate the main pipeline at Batu 7 was being refined with the Works Ministry, taking into account challenges posed by soft ground conditions and land reclamation works in the area.