River, hilly terrain pose challenges to Sabah power restoration

RANAU: Field teams face two main challenges in building the temporary Emergency Recovery System (ERS) tower to restore the 275kV transmission line supplying electricity to Sabah’s East Coast.

Sabah Electricity chief operating officer Mohd Riza Zalmee Mohd Ghazali said the first challenge involves lifting the lines across a fast-flowing river with help from the fire department, and the second is the hilly terrain.

“In the more hilly areas, we need to clear or find routes so workers can access the site and pull the second line to reach the ERS tower,” he told Bernama.

He said the first phase, erecting the temporary ERS tower structure, was completed as of yesterday, though the technical team is still installing the guy wires.

Riza Zalmee said construction is split into two phases, with the second involving stringing the transmission lines, which is already in progress today.

“The second phase involves pulling two lines to the ERS tower, one of them from across the river,” he said.

Meanwhile, Sabah Electricity chief executive cfficer Datuk Mohd Yaakob Jaafar said the utility and its contractors had installed three conductor cables on the temporary ERS tower today.

He said the technical team is now pulling conductor cables from both the collapsed T313 and the T314 to the ERS tower.

“Our target today is to complete three cables for the first circuit,” he said.

The T313 transmission tower, on the banks of Sungai Liwagu in Kampung Sagindai Lama along Jalan Ranau-Telupid, collapsed due to erosion from continuous rain and the fast-flowing river.

The incident affected 153,599 registered consumers. Sabah Electricity aims to restore supply by Dec 2 or earlier.