RANAU: Work to reconnect the electricity transmission line supplying Sabah’s East Coast is expected to be completed tonight, with recovery efforts on the East-West transmission line now about 70 per cent complete.
Sabah Electricity chief executive officer Datuk Mohd Yaakob Jaafar said conductor cable installation work on the Emergency Restoration System (ERS) tower in Kampung Sagindai here was underway to reconnect the transmission line disrupted following the collapse of tower T313 on Thursday.
He said the temporary tower was in place by noon yesterday, while conductor cable stringing was being carried out today as scheduled.
“As of 12.30pm, five conductors have been strung, while another is being installed to complete the first circuit.
“To ensure safety before the line is re-energised, inspections are being carried out using a helicopter carrying technical personnel to patrol the transmission line from Kota Kinabalu to Sandakan,” he told reporters at the ERS tower site.
He said the inspections were aimed at ensuring there were no obstructions along the transmission line route before electricity supply was restored.
Once the ERS tower installation was fully completed, it would be able to support transmission of up to 320 megawatts (MW), he added.
On the collapsed T313 tower, Mohd Yaakob said it was built in 2007 and was located 106m from the banks of the Sungai Liwagu.
He said sand embankments had previously been placed at the tower site, but erosion and river currents were among the factors identified as contributing to the collapse, as the tower’s foundation had become suspended.
Yaakob said 663 electricity transmission poles along the Kota Kinabalu-Sandakan route, including one identified in Sipitang near a river, were also being monitored closely.
Yaakob said the 250km transmission line from Kota Kinabalu to Sandakan was usually inspected by helicopter every three months, with more frequent inspections during the rainy season.
Transporting equipment to build the ERS tower was also a challenge for more than 100 personnel working at the site, as they had to use the suspension bridge over Sungai Liwagu in Kampung Sagindai Lama as the only main access route, he said.
“The biggest challenge was crossing the river with the conductor cable, as it is heavy and could be damaged if it were dragged through the river. The Fire and Rescue Department also assisted us yesterday, but we were unsuccessful because the current was strong.
“Fortunately, we had a conductor that was still connected, and our personnel crossed the river using it to pull the pilot wire. The weather was also quite good, which helped us expedite the recovery work,” he said.
He said the ERS tower site was initially proposed to be built on the opposite side of the river, which would have taken six days, but the location was changed due to unsuitable ground conditions.
Transmission tower T313, located on the banks of the Sungai Liwagu in Kampung Sagindai Lama along the Ranau-Telupid Road, collapsed due to erosion caused by continuous rain and strong river currents.
The incident initially affected 153,599 registered Sabah Electricity consumers, with the utility previously targeting electricity supply restoration by Dec 2 or earlier.