BUTTERWORTH: Package 1 of the Juru-Sungai Dua traffic dispersal project has achieved 54.61 per cent progress as of last week.
The scope of Package 1 includes upgrading access ramps at the East-West interchange roundabout and constructing a new bridge along Jalan Tun Hussein Onn to boost road capacity and ease local congestion.
“Subsequent phases are also moving forward, with Packages 2 to 5 currently in the final tendering stage,” Plus Malaysia Bhd said today.
The project, estimated to cost RM3 billion, is expected to ease congestion, with 30 per cent of traffic projected to shift to the new direct Juru-Sungai Dua route.
The 17.3km project, spanning three main districts, is designed to benefit over 200,000 daily road users.
Current travel time is expected to be reduced from one hour to just 20 minutes during peak hours.
According to Plus, Packages 2 and 5 cover roadworks between the Juru toll plaza and Juru lay-by, as well as the stretch from the Samagagah lay-by to the Sungai Dua toll plaza.
Meanwhile, Packages 3 and 4 involve building elevated sections and interchanges linking the Juru lay-by and Samagagah lay-by.